Visitors to the Scott Library will be aware of the many changes underway this summer.
First Floor
Currently new flooring is being installed in Central Square, first floor of Scott. New wall colours will be coming soon to compliment the new furniture and other improvements in the study area on the first floor. Four group study rooms are replacing rooms that have been dismantled to make room for a new computing site next to the copy center. The new floor at the entrance to the Library should be completed over the Canada Day holiday weekend.
Third Floor
The new compact shelving system being installed on the third floor is progressing, the first two sections, representing 10,000 linear feet of shelving is having the finishing touches applied and the remaining two sections start assembly this week. Once the shelving is fully installed, the collections will be returned to Scott from their temporary locations.
Both areas of renovation are running ahead of schedule which will be good news!