1st Floor renovation update
- painting of the walls in the Accessibility Services area and Circulation department started Friday July 7th after library hours.
- workers will begin laying the tile floor in the front foyer of the library on Friday July 13, again working after the library closes for the evening.
- during the week of July 13-20 new carpet will be laid in Accessibility Services and the Circulation department.
3rd Floor renovation update
- 4 of the 6 rails for the new compact shelving has been installed
- the drilling/coring for the electrical wiring will begin on the evening of Monday July 9 and continue into the week.
Of note is that on completion of this renovation project over 300 new wired workstations for students will be added to the library.