Tentative Schedule
(subject to change)
3rd Floor
| April 16-27 | Relocation of books from 2nd and 5th floors to storage and backfill from 3rd floor, 3rd floor to HNES |
| Apr 30 – May 11 |
Pack and store books from 3rd floor |
| May 14-25 |
Dismantle and remove existing shelving |
| May 28-29 |
Carpet removal |
| May 30 – Jun 1 |
Tile and lighting work |
| Jun 4-15 |
Rail and floor installation |
| Jun 18-19 | Carpeting installation |
| Jun 20 – Jul 13 |
System installation |
| July 16 – Aug 10 | Return books |
1st Floor
| April 30 – May 14 |
-Remove existing carrels -Replace some of the carrels on the 4th and 5th floors with some of these -Install additional carrels on the balconies on the 3rd, 4th and 5th floors |
|
May 14 – Jun 11 |
-Network drops and electrical outlets to be installed -Carpet and vinyl tiles to be installed -Walls to be painted -Sound masking to be installed -New glaze partition wall to be installed -Reassemble 4 group study rooms -Circulation and exit desks to be replaced -Existing computers and printers to be relocated |
|
Jun 11-25 |
-Furniture arrives -Set-up may begin |